Public Works Department Project List

Map Gallery

Public Works Gallery of Maps

 

Projects Currently in Progress

Advisories and delays are posted in WAZE for those using the app.

  • South Edgewood Drive West of McKeel Academy to East of Taft - Work Delayed

    Due to the recent storm event and Water Department water main upgrade and relocation schedule to start in October, this project has been delayed till further notice.

    City of Lakeland crews will begin drainage improvements, sidewalk and driveway construction on the north side of the roadway. Motorists can expect daily lane closure traffic control and flagging operations in place. Motorists and pedestrians can also expect delays and should use alternate routes when available. This project is expected to take approximately six (6) months to complete.

    Contact Mike Slaton, Supervisor, at (863) 834-3316 with questions and continue to check (863) 834-ROAD (7623) for updated information. Please visit http://www.lakelandgov.net for updated information. Follow the City of Lakeland Facebook page at http://www.facebook.com/Lakelandgov.

  • Fiscal Year 2025 Paving Plan (October 2024 through September 2025)

    A list of the roads in the 2025 paving plan is below with the tentative schedules for the contracted work.

    On-Street From To Dates (in 2025)
    E. Main St Bartow Rd Lake Bonny Dr. E Feb 26 - Mar 5
    S. Lincoln Ave Ariana St W. Edgewood Dr Mar 4 - 7
    E. Bay St Massachusetts Ave N. Lake Ave Mar 6 - 10
    N. Ruth Ave W. Parker St Memorial Blvd Mar 7 - 11
    E. Edgewood Dr S. Florida Ave New Jersey Rd Mar 10 - 17
    On-Street From To Dates (in 2025)
    E. Parker St Lake Parker Ave N. Massachusetts Ave TBD
    Spinnaker Dr Edgewater Beach  End Mar 14 - 21
    Buena Dr Edgewater Beach  N. Lake Parker Dr Mar 14 - 21
    Greenview Dr Edgewater Beach  N. Lake Parker Dr Mar 14 - 21
    Evergreen Dr Edgewater Beach  N. Lake Parker Dr Mar 14 - 21
    Parker Point Ln Edgewater Beach  N. Lake Parker Dr Mar 14 - 21
    Maple St N. Orange Ave US 98 N Mar 27 - Apr 1
    N. Orange Ave Maple St Gib-Galloway Rd Mar 27 - Apr 1
    Wedgewood Estates Bl US 98 N Carpenters Way Mar 25 - 28
    S. Edgewood Dr Taft Ave Bartow Rd TBD
    Cherokee Trl Seminole Trl Maxwell St Mar 20 - 25
    E. Main St Massachusetts Ave N. Lake Ave Mar 28 - Apr 4
    S. Lake Ave E.Main St E. Walnut St Mar 28 - Apr 4
    Pawnee Trl Cherokee Trl Pueblo Trl Mar 20 - 25

    Upcoming Reclamite Treatment

    On-Street From To Dates (in 2025)
    Rose St Ingraham Ave N Fern Rd N Feb 17
    Webster Begin 10th St Feb 18
    Success Ave Lake Hollingsworth Lake Morton Dr Feb 19
    South Blvd Belmar St Lake Morton Dr Feb 19
    Carolina Ave Kerneywood Dr Beacon Rd Feb 19
    7th St Parkhurst Ave Webster Ave N Feb 18
    Main St W Central Ave George Jenkins Bl Feb 18
    Central Ave Main St W Olive St Feb 18
    E Park St S Florida Ave Success Ave Feb 19
    Lake Hunter Dr King Ave Sikes Blvd Feb 18
    E Orange St S Lake Ave Bartow Rd Feb 17
    Park Dr Venice Way New Jersey Rd Feb 20
    Stanhope Ave Park Dr Glendale St Feb 20
    Drewery Ave Park Dr Glendale St Feb 20
    Atlanta Ave Park Dr Glendale St Feb 20
    Bellwood Ave Park Dr Glendale St Feb 20
    Pineway Ave Park Dr Glendale St Feb 20
    Spanish Oaks Blvd Highway 33 End Feb 17
    Spanish Oaks Dr Spanish Oaks Blvd Spanish Oaks Blvd Feb 17
    Spanish Oaks Ln Spanish Oaks Blvd Emd Feb 17

     

    Contact Troy Williams, Pavement Coordinator, at (863) 834-3315 with questions and continue to check (863) 834-ROAD (7623) for updated information. Please visit http://www.lakelandgov.net for updated information. Follow the City of Lakeland Facebook page at http://www.facebook.com/Lakelandgov.

  • Emma Street and North Scott Avenue Improvements - Work Begins December 2, 2024

    Starting December 2, 2024, City of Lakeland crews will begin sidewalk, curb, driveway, and ADA curb ramps improvements project.  This work will be done on Emma Street from North Scott Avenue to Florida Avenue and on North Scott Avenue from Emma Street to Parker Street West.  Daily road closures can be expected. Motorists and pedestrians can also expect delays and should use alternate routes when available. This project is expected to take approximately seven (7) months to complete.

    Contact Chris Sadler, Supervisor, at (863) 834-3309 with questions and continue to check (863) 834-ROAD (7623) for updated information. Please visit http://www.lakelandgov.net for updated information. Follow the City of Lakeland Facebook page at http://www.facebook.com/Lakelandgov.

  • Easton Drive Street Repair - Work Begins February 24, 2025

    In preparation for re-paving this brick street, City crews will have to install concrete ribbon tie-ins on the east and west end of the block of Easton Drive (between Cambridge Avenue and Fairmount Avenue) for the asphalt paving to tie into and the existing brick that will remain in place. The concrete portion of this project is scheduled for the week of February 24, 2025 and is expected to take up to a week to complete. The paving is scheduled for March 10 or 11, 2025 and will be completed in one day. The speed hump will be scheduled within a couple of weeks after paving. During each aspect of this project, traffic control devices will be in place to guide motorists through the work zone, or a detour will be in place when closing this section of roadway is necessary.

    This section of Easton Drive was part of a brick street restoration project five years ago.  The asphalt was removed and restored to the original brick street that existed under the asphalt. During heavy rain events, this section of brick street gets washed out severely and creates a safety issue for motorists. This has happened several times and no remedies have been found to prevent this issue. Once paved, we are also going to install a traffic calming hump on this block to address concerns of speeding.

    Contact Mike Slaton, Supervisor, at (863) 834-3316 with questions and continue to check (863) 834-ROAD (7623) for updated information. Please visit http://www.lakelandgov.net for updated information. Follow the City of Lakeland Facebook page at http://www.facebook.com/Lakelandgov.

  • Cleveland Heights Blvd Turn Lane Modification - Work Begins February 10, 2025

    Starting February 10, 2025 City of Lakeland crews will begin modification to south bound turn lane at Westover Street. Daily Lane closures can be expected. Motorists and pedestrians can also expect delays and should use alternate routes when available. This project is expected to take approximately three (3) months to complete.

    Contact Chris Sadler, Supervisor, at (863) 834-3309 with questions and continue to check (863) 834-ROAD (7623) for updated information. Please visit http://www.lakelandgov.net for updated information. Follow the City of Lakeland Facebook page at http://www.facebook.com/Lakelandgov.

Projects in Planning and Design for Future Consideration

Projects that have been Completed in the Past Year